Skip to Main Content
IBM Sustainability Software - Ideas Portal


This portal is to open public enhancement requests against the products and services belonging to IBM Sustainability Software. To view all of your ideas submitted to IBM, create and manage groups of Ideas, or create an idea explicitly set to be either visible by all (public) or visible only to you and IBM (private), use the IBM Unified Ideas Portal (https://ideas.ibm.com).


Shape the future of IBM!

We invite you to shape the future of IBM, including product roadmaps, by submitting ideas that matter to you the most. Here's how it works:

Search existing ideas

Start by searching and reviewing ideas and requests to enhance a product or service. Take a look at ideas others have posted, and add a comment, vote, or subscribe to updates on them if they matter to you. If you can't find what you are looking for,

Post your ideas
  1. Post an idea.

  2. Get feedback from the IBM team and other customers to refine your idea.

  3. Follow the idea through the IBM Ideas process.


Specific links you will want to bookmark for future use

Welcome to the IBM Ideas Portal (https://www.ibm.com/ideas) - Use this site to find out additional information and details about the IBM Ideas process and statuses.

IBM Unified Ideas Portal (https://ideas.ibm.com) - Use this site to view all of your ideas, create new ideas for any IBM product, or search for ideas across all of IBM.

ideasibm@us.ibm.com - Use this email to suggest enhancements to the Ideas process or request help from IBM for submitting your Ideas.

Status Not under consideration
Categories Planning
Created by Guest
Created on May 19, 2025

Baselining of schedule (plan) is currently unavailable in EWm plan. Baselining would allow the date sets previously planned to be made available as records for all future comparison with current set of start and end dates

Baselining is a best practice followed in project management in order to retain data on previously agreed baseline. Current set of dates are compared to the last baseline to show the departure of current plan in comparison to the baseline. This facility is absent. In the past when this query was raised i was told snapshots are working as baselines. However taking snapshot is not the same as baselining as taking a planned or proposed snapshots changes the start date of all activities to one specific date which is today's date. Therefore, there is no option to keep the current set of planned dates for me to use as a baseline and track my schedule changes. You can refer to baselining in Microsoft Project for further details on baselining a project schedule

Idea priority Urgent
Needed By Yesterday (Let's go already!)
  • Guest
    May 22, 2025
    We have the functionality of creating snapshots for Plans. They are like baselines and can also be compared with different versions. Some useful links are:
    Jazz.net Article: Effective Planning using Snapshots
    IBM Docs: Plan Snapshots