Skip to Main Content
IBM Sustainability Software - Ideas Portal
Hide about this portal


This portal is to open public enhancement requests against the products and services belonging to IBM Sustainability Software. To view all of your ideas submitted to IBM, create and manage groups of Ideas, or create an idea explicitly set to be either visible by all (public) or visible only to you and IBM (private), use the IBM Unified Ideas Portal (https://ideas.ibm.com).


Shape the future of IBM!

We invite you to shape the future of IBM, including product roadmaps, by submitting ideas that matter to you the most. Here's how it works:

Search existing ideas

Start by searching and reviewing ideas and requests to enhance a product or service. Take a look at ideas others have posted, and add a comment, vote, or subscribe to updates on them if they matter to you. If you can't find what you are looking for,

Post your ideas
  1. Post an idea.

  2. Get feedback from the IBM team and other customers to refine your idea.

  3. Follow the idea through the IBM Ideas process.


Specific links you will want to bookmark for future use

Welcome to the IBM Ideas Portal (https://www.ibm.com/ideas) - Use this site to find out additional information and details about the IBM Ideas process and statuses.

IBM Unified Ideas Portal (https://ideas.ibm.com) - Use this site to view all of your ideas, create new ideas for any IBM product, or search for ideas across all of IBM.

ideasibm@us.ibm.com - Use this email to suggest enhancements to the Ideas process or request help from IBM for submitting your Ideas.

Planning duration on routes doesnt take into account the number of assets being maintained.

See this idea on ideas.ibm.com

Currently using Maximo 7.6.

When creating a PM with a route attached, I am creating it using a jobplan of specific tasks and duration to perform on a specific asset.

My problem is how it then generates the assignment duration on the work order.

If you have a jobplan for example 0.5 hours, and you have 10 assets to maintain in the route. Even if you add in a duration of 5.0 hours into the PM front screen, the jobplan time of 0.5 still seems to override everything when the work orders are created. The issue this creates is that the work orders then generate with the 0.5 hours on the assignment no matter if you have 1 asset or 20 assets against the route, which makes planning the actual time required to undertake the work very difficult.

I have found it is a similar issue when creating Parent/Child PMs. The Parent doesn't automatically add up the duration of all the Children PMs for planning purposes. To rectify this in my role, I have created an empty jobplan (multiple different versions of) for all the parents (this tells the PM the duration and skill level required to generate the parent WO with).

Is there a way of doing this more accurately?

Thanks 

Molly Gill

Idea priority Low
Needed By Not sure -- Just thought it was cool