Skip to Main Content
IBM Sustainability Software - Ideas Portal


This portal is to open public enhancement requests against the products and services belonging to IBM Sustainability Software. To view all of your ideas submitted to IBM, create and manage groups of Ideas, or create an idea explicitly set to be either visible by all (public) or visible only to you and IBM (private), use the IBM Unified Ideas Portal (https://ideas.ibm.com).


Shape the future of IBM!

We invite you to shape the future of IBM, including product roadmaps, by submitting ideas that matter to you the most. Here's how it works:

Search existing ideas

Start by searching and reviewing ideas and requests to enhance a product or service. Take a look at ideas others have posted, and add a comment, vote, or subscribe to updates on them if they matter to you. If you can't find what you are looking for,

Post your ideas
  1. Post an idea.

  2. Get feedback from the IBM team and other customers to refine your idea.

  3. Follow the idea through the IBM Ideas process.


Specific links you will want to bookmark for future use

Welcome to the IBM Ideas Portal (https://www.ibm.com/ideas) - Use this site to find out additional information and details about the IBM Ideas process and statuses.

IBM Unified Ideas Portal (https://ideas.ibm.com) - Use this site to view all of your ideas, create new ideas for any IBM product, or search for ideas across all of IBM.

ideasibm@us.ibm.com - Use this email to suggest enhancements to the Ideas process or request help from IBM for submitting your Ideas.

Status Future consideration
Created by Guest
Created on Apr 18, 2024

Consider Resource / Crew Assignment when control the Resource load and Availability in Graphical Scheduling

How it works today

During the Planning/Scheduling phase, Graphical Scheduling is used to decide whether work orders can be executed based on resource and crew availability.

The Graphical Scheduling calculates availability by dealing with Calendar/Shift/Modify Availability of resources (this functionality for crew is missing).

The system does not consider if resources or crews are already assigned to other work orders that are external to the Scheduling project.


Sample scenario

For example: if in the organization there are 5 electricians and the work orders of the Scheduling project require 3 electricians for a specific date, the system will show an availability of 5 (multiplied by shift hours), but if 3 of these electricians are assigned to other work orders for the same date, the actual availability should be 2 for that date.


How should it work and why is it useful?

The system should calculate the availability of resources also considering the assignments to other work orders external to the project and it should consider the Modify Availability also for crews.

This will be useful for the planner who is informed of the real availability of the resources/crews and not just their total amount.

Idea priority High
Needed By Quarter